Mary Alice Reporting – Motorists are asked to continue using caution in Uhrichsville for a bridge project.

The Ohio Department of Transportation started the Trenton Avenue bridge work earlier this year and they are close to the half-way mark.

District 11 Public Information Officer Lauren Borell says crews recently poured the bridge deck on one side.

“In the coming week folks will starting seeing some lane changes. We have traffic maintained on one side and we’ll be flipping it to the other side to finish that work.”

The completion date is October 31st; however, due to heavy rainfall at the start of summer, that has been pushed back to late fall.